Construction
Update as of November 15, 2002
Period 7 to 21 November
2002
UTILITY SHUTDOWNS:
   - An 8 hour electrical shutdown that will affect the Dupont
   Building is in the process of being scheduled. Tentative date is
   November 23rd.
WORK AREAS:
Cornell Library
   - There is no work scheduled in or on Cornell during this
   period. 
Cornell Addition (a.k.a. Biology/ Commons Wing)
   - Mechanical work is focused in the mechanical room in the lower
   level. The curtain wall (exterior wall made of aluminum framing
   and glass) at the Commons is being installed. Roofing at this area
   will commence during the next two weeks. Installation of the glass
   in the windows of the Biology wing and 200-seat Lecture Hall is
   nearly complete. Installation of the Commons elevator is
   continuing. The granite and schist veneers will continue on the
   40-seat classroom and walls in the courtyard between the Commons
   and Dupont.  Interior walls in Biology have been closed and will
   be taped and spackled in the next week with prime painting to
   follow.  Installation of lab casework will begin in the next two
   weeks.
Chiller Plant
   - Mechanical piping and electrical services are being installed.
   Chiller piping is being completed and tested.  
Chemistry/Astronomy Wing
   - Rough-in of mechanical and electrical services is occurring on
   all floors. The granite panels and schist veneer are being
   installed on the north and south walls. Interior partitions have
   been framed on part of the second and first floors; this work is
   continuing. The penthouse duct and piping is being completed and
   tested.
Martin Building
   - Mechanical piping is being installed in the basement crawl
   space. The steam service is being connected to the Cornell
   addition.  Work is expected to continue for another two
   weeks.
SITEWORK:
   - Two additional trenches are being cut in the North Quad to
   complete sanitary and data line tie-ins outside the construction
   fence. The work area is enclosed in orange snow fence.
- The extension of water and fire lines to the Chiller Building
   along the north edge of the service drive behind Dupont is
   complete.
PEDESTRIAN / VEHICULAR ACCESS:
   - The service drive along the east face of the Chemistry
   Building will remain closed for the next two weeks while the
   granite panel installation continues. Traffic has been re-routed
   through the Rugby parking lot.
- Deliveries of drywall, glass, stone, ductwork and mechanical
   equipment will be on-going.
- Parking along Whittier Place is prohibited during the hours of
   7 a.m. to 5 p.m., Monday through Friday.
- There is continuing pressure on parking. Barclay White is
   continuing to reorganize their operation over the next few weeks
   to free up a total of 22-23 spaces in the Dupont lot, which should
   help alleviate the problem.
- A casework delivery is expected early the week of
   11/18. 
NOISE, VIBRATION, DUST, ODORS
   - There will be some noise from delivery trucks, cranes and saws
   throughout this period. The noise is not expected to be disruptive
   to nearby buildings.
return to Home Page
Send message to the chair
of the Science Project User's Group, Rachel Merz
(rmerz1@swarthmore.edu)
For inquiries regarding construction issues, send message to
construction@swarthmore.edu
last updated 11/18/02