Construction
Update as of November 15, 2002
Period 7 to 21 November
2002
UTILITY SHUTDOWNS:
- An 8 hour electrical shutdown that will affect the Dupont
Building is in the process of being scheduled. Tentative date is
November 23rd.
WORK AREAS:
Cornell Library
- There is no work scheduled in or on Cornell during this
period.
Cornell Addition (a.k.a. Biology/ Commons Wing)
- Mechanical work is focused in the mechanical room in the lower
level. The curtain wall (exterior wall made of aluminum framing
and glass) at the Commons is being installed. Roofing at this area
will commence during the next two weeks. Installation of the glass
in the windows of the Biology wing and 200-seat Lecture Hall is
nearly complete. Installation of the Commons elevator is
continuing. The granite and schist veneers will continue on the
40-seat classroom and walls in the courtyard between the Commons
and Dupont. Interior walls in Biology have been closed and will
be taped and spackled in the next week with prime painting to
follow. Installation of lab casework will begin in the next two
weeks.
Chiller Plant
- Mechanical piping and electrical services are being installed.
Chiller piping is being completed and tested.
Chemistry/Astronomy Wing
- Rough-in of mechanical and electrical services is occurring on
all floors. The granite panels and schist veneer are being
installed on the north and south walls. Interior partitions have
been framed on part of the second and first floors; this work is
continuing. The penthouse duct and piping is being completed and
tested.
Martin Building
- Mechanical piping is being installed in the basement crawl
space. The steam service is being connected to the Cornell
addition. Work is expected to continue for another two
weeks.
SITEWORK:
- Two additional trenches are being cut in the North Quad to
complete sanitary and data line tie-ins outside the construction
fence. The work area is enclosed in orange snow fence.
- The extension of water and fire lines to the Chiller Building
along the north edge of the service drive behind Dupont is
complete.
PEDESTRIAN / VEHICULAR ACCESS:
- The service drive along the east face of the Chemistry
Building will remain closed for the next two weeks while the
granite panel installation continues. Traffic has been re-routed
through the Rugby parking lot.
- Deliveries of drywall, glass, stone, ductwork and mechanical
equipment will be on-going.
- Parking along Whittier Place is prohibited during the hours of
7 a.m. to 5 p.m., Monday through Friday.
- There is continuing pressure on parking. Barclay White is
continuing to reorganize their operation over the next few weeks
to free up a total of 22-23 spaces in the Dupont lot, which should
help alleviate the problem.
- A casework delivery is expected early the week of
11/18.
NOISE, VIBRATION, DUST, ODORS
- There will be some noise from delivery trucks, cranes and saws
throughout this period. The noise is not expected to be disruptive
to nearby buildings.
return to Home Page
Send message to the chair
of the Science Project User's Group, Rachel Merz
(rmerz1@swarthmore.edu)
For inquiries regarding construction issues, send message to
construction@swarthmore.edu