Construction
Update as of November 16, 2001
Period 28 November - 12 December
2001
UTILITY SHUTDOWNS:
- There will be a major electrical shutdown over the holiday
break between Christmas and New Year's Day. The College is working
with Riteway to schedule this work. Facilities will notify
faculty, staff and students.
WORK AREAS:
Dupont Research Annex
- Temporary partitions are being installed along the exterior
wall of Room 242.
Dupont Physics Wing
- The temporary platform at the connector to Cornell was
replaced with a more permanent structure on Wednesday, 11/21.
Rugby Field
- The new access road was paved with a base course of asphalt
and is open to traffic.
- Stockpiling of topsoil and fill is complete. Modifications to
the swale will occur within the next week. Additional fill
material has being stockpiled alongside the topsoil for use as
backfill against the Science Center foundations.
North Quad
- Note the pathways marked with signs and arrows painted on the
ground that lead from Beardsley around to the north entrance to
Dupont.
Cornell Library
- The temporary platform at the connector to Dupont was replaced
on Friday, 11/23 with a more permanent structure.
PEDESTRIAN / VEHICULAR ACCESS:
- The new service drive alongside the Research Annex was paved
and re-opened to traffic this week so that connection of the
underground utilities from the drive to the new manhole can be
completed.
- On Thursday, 12/6 from 7:00 a.m. to 6:00 p.m., the service
drive will be closed for one day from the Dupont Visitors
Lot back to Lang Music and Lang PAC. A notice to the College
community about the prohibition of parking along the service drive
for that day has been sent.
- Parking along Whittier Place is prohibited during the hours of
7 a.m. to 5 p.m., Monday through Friday.
- Electrical work inside the manhole in the Hicks lot is
continuing.
NOISE, VIBRATION, DUST, ODORS
- Installation of the remaining chilled and hot water piping in
the south end of the DuPont Visitors lot will create some
dust in the area.
DELIVERIES / HEAVY EQUIPMENT:
- Paving of the service drive behind the Research Annex will
require heavy machinery on site on Thursday 12/6.
return to Home Page
Send message to the chair
of the Science Project User's Group, Rachel Merz
(rmerz1@swarthmore.edu)
For inquiries regarding construction issues, send message to
construction@swarthmore.edu
last updated 12/01/01
webmaster