Construction
Update as of July 21, 2003
Period 18 through 31 July
2003
UTILITY SHUTDOWNS:
- Gas and water services have been shut down permanently to the
Dupont Building and the Research Annex. Electrical service in the
Science Center will be interrupted during this period so that
Dupont and the Annex can be disconnected. The shutdown will be
coordinated through Facilities.
WORK AREAS:
Cornell Library
- A portion of the roof above the Cornell Library will be
replaced during this period.
Cornell Addition (a.k.a. Biology/ Commons Wing)
- Punchlist work will take place throughout the building during
the rest of the summer. Skanska will coordinate room access
through Facilities.
Chiller Plant
- No work during this period.
Chemistry/Astronomy Wing
- The College has taken occupancy of this building. The
Chemistry and Astronomy faculty will complete their relocation of
office materials and laboratory equipment by 7/21. There will be
work throughout the building to finish wood trim, fumehood testing
and programming, mechanical system balancing and other punchlist
work. The mechanical penthouse floor topping will be applied
during this period. Application of metal siding on the building
exterior will continue.
Martin Building
- The curtainwall framing on the bridge will be installed during
this period. The new structural steel and metal deck for the
second floor of Martin will be erected.
Existing Dupont Research Annex
- Installation of the new handrails at the new stairs will start
during the week of 7/28. That stair is for emergency egress only,
until the rails are completed. Demolition of the Annex interior
will start during this period.
Existing Dupont Physics Wing
- Demolition will continue in the Physics wing.
SITEWORK:
- Rough grading and placement of paving in front of the Commons
will continue during this period.
PEDESTRIAN / VEHICULAR ACCESS:
- The service drive along the east face of the Chemistry
Building will be subject to occasional lane restrictions as
material deliveries are off-loaded. A curb cut has been made and
a lay-by lane will be paved for delivery trucks near the east
entry.
- Parking along Whittier Place is prohibited during the hours of
7 a.m. to 5 p.m., Monday through Friday.
- Work on the bridge that will connect Martin Building to the
Cornell Addition is underway and will continue through the end of
August. The path at grade between Martin and Cornell is closed.
Access to Cornell Library is through the new entrance at the
intersection of the Cornell Addition and the Commons. Directional
signs have been posted.
- Demolition work inside the Dupont Physics Wing continues.
There will be dust and noise associated with this work. Please
also be aware of workers traveling through corridors with trash
carts.
NOISE, VIBRATION, DUST, ODORS
- There may be some construction related noise, dust and
vibration during the demolition in Martin Building and throughout
the Dupont Physics Wing.
- Earthmoving operations in the lawn area may produce dust when
the ground dries out.
- There will be some noise from delivery trucks, cranes and saws
throughout this period. These activities may be disruptive to
nearby buildings.
return to Home Page
Send message to the chair
of the Science Project User's Group, Rachel Merz
(rmerz1@swarthmore.edu)
For inquiries regarding construction issues, send message to
construction@swarthmore.edu
last updated 7/22/03