Construction
Update as of March 21, 2003
Period 21 March - 3 April
2003
UTILITY SHUTDOWNS:
- There are no utility shut-downs scheduled for this
period.
WORK AREAS:
Cornell Library
- There is no work scheduled in Cornell Library during this
period.
Cornell Addition (a.k.a. Biology/ Commons Wing)
- Metal cladding on the soffits at the main Commons roof will
continue during the next two weeks. The granite and schist veneers
were completed on the 40-seat classroom. Slate and VCT flooring as
well as casework will continue in the Commons. The 200-Seat
Lecture Hall seating was installed and the audio-visual equipment
installation is underway. This area will undergo a final State
L&I inspection on 24 March and Physics faculty will occupy the
lower level on that date. Carpeting will be installed in the
Commons and 200 Seat Lecture hall will be installed during this
period. The temporary walls between the Cornell Addition and the
Commons will be removed during this period. The Coffee Bar
casework will be installed during this period.
Chiller Plant
- The acoustical roof screen installation will continue through
this period. Chiller pipe flushing will continue through this
period.
Chemistry/Astronomy Wing
- Pressure testing of mechanical and electrical services is
continuing in the Astronomy wing. Schist stone installation is
underway outside the 80 Seat Lecture Hall. Interior partition
framing is continuing on the Astronomy first floor. One penthouse
air handler was started up to supply temporary heating. Window
installation is in progress. The stainless steel siding is being
installed on the penthouse. Walls in the Chemistry wing are being
painted. Fume hoods have been delivered and installation has
started. The first shipment of Chemistry lab casework will arrive
next week.
Martin Building
- Work on the connecting bridge is underway. There will be some
noise associated with the excavation in the area between Martin
and Cornell for the bridge footings and piers.
Existing Dupont Research Annex
- The first and second floor labs at the southeast corner of the
Annex were vacated and demolition work is nearly complete. The
work to build footings and walls for a new stairwell will continue
through June and may expose adjacent areas to construction
noise.
SITEWORK:
- The North Quad storm tie-in is done and the infiltration
cistern is being installed outside the Commons.
- The underground connection of HVAC piping between the Commons
and Chemistry wings has been completed and the area is being
backfilled.
PEDESTRIAN / VEHICULAR ACCESS:
- The service drive along the east face of the Chemistry
Building will be subject to occasional lane restrictions as
material deliveries are off-loaded.
- Parking along Whittier Place is prohibited during the hours of
7 a.m. to 5 p.m., Monday through Friday.
- A security guard is metering the number of construction
vehicles that enter the parking lots.
- Work on the bridge that will connect Martin Building to the
Cornell Addition is underway and will continue through the end of
August. The path at grade between Martin and Cornell is closed.
Access to Cornell Library is through the new entrance at the
intersection of the Cornell Addition and the Commons. Directional
signs have been posted.
NOISE, VIBRATION, DUST, ODORS
- There may be some construction related noise evident once the
temporary partitions inside the Biology wing are removed.
- There will be some noise from delivery trucks, cranes and saws
throughout this period. These activities may be disruptive to
nearby buildings.
return to Home Page
Send message to the chair
of the Science Project User's Group, Rachel Merz
(rmerz1@swarthmore.edu)
For inquiries regarding construction issues, send message to
construction@swarthmore.edu
last updated 3/21/03
webmaster