Construction
Update as of April 25, 2002
Period 29 April thru 8 May
2002
UTILITY SHUTDOWNS:
- There are no utility shut-downs planned for this period.
WORK AREAS:
Cornell Library
- The second floor of the library remains in operation on the
west side of the temporary wall. Removal of the roof is proceeding
on the east side, in preparation for building a mechanical
penthouse on a new, flat roof. This work will continue through
the rest of the spring semester and the summer. At the end of
July, the penthouse will be complete and the temporary wall on the
second floor will be removed. The book shelves will be reinstalled
and the carrels will be put back in place to prepare for the new
academic year.
Cornell Addition (a.k.a. Biology/ Commons Wing)
- Excavation and placement of underground utilities in the
Commons and Lecture Hall areas is complete. Concrete has been
poured on the steel decks for the first and second floor adjacent
to Cornell. The lower level concrete floor adjacent to Cornell
will be poured in the next two weeks. Concrete pours for the
columns on the lower level in the Commons area are in progress.
The Commons ground-level floor will be poured at the end of next
week. Mock-ups of stone finishes are in progress.
Chiller Plant
- The steel erection is complete. The footings and foundation
block walls are complete. The under-slab utilities are installed.
The concrete slab on grade will be completed next week. Erection
of the block and brick walls will start this week.
Chemistry Wing
- Excavation and foundations are in progress. The precast
concrete panels and windows on the east face of the existing
Dupont Chemistry wing will be removed beginning 29 April in
preparation for steel erection that will start approximately May
13.
PEDESTRIAN / VEHICULAR ACCESS:
- There will be numerous truck deliveries of structural steel on
5/8, 5/9 and throughout the week of 5/13. Normal traffic may be
routed through the rugby parking lot as trucks are unloaded on the
service drive adjacent to the new Chemistry wing.
- There will be intermittent lane closures of the service drive
between Dupont and Cornell in late-May.
- Parking along Whittier Place is prohibited during the hours of
7 a.m. to 5 p.m., Monday through Friday.
- The construction work force is getting larger. Thank you for
your cooperation in respecting the areas designated as
Construction Parking by using the rugby and Dupont parking
lots.
NOISE, VIBRATION, DUST, ODORS
- There will be a truck mounted drill rig on site next week to
drill a hole for the elevator piston in the new
Chemistry/Astronomy wing.
- There will be some noise from concrete trucks throughout this
period. The noise is not expected to be disruptive to nearby
buildings.
- There may be some dust generated by the on-going excavation of
the Chemistry Wing footings alongside the service drive.
DELIVERIES / HEAVY EQUIPMENT:
- Expect deliveries of reinforcing steel, concrete and masonry
throughout this period.
return to Home Page
Send message to the chair
of the Science Project User's Group, Rachel Merz
(rmerz1@swarthmore.edu)
For inquiries regarding construction issues, send message to
construction@swarthmore.edu
last updated 4/29/02
webmaster