Construction
Update as of August 2, 2002
Period 1 to 15 August
2002
UTILITY SHUTDOWNS:
- No major shutdowns are planned in the next two weeks.
WORK AREAS:
Cornell Library
- Construction has been substantially completed on the second
floor. The book shelves have been reinstalled and re-shelving of
the collection is underway. Minor electrical and mechanical work
will occur over the next two weeks. The stair at the northeast
corner of Cornell will be closed until early August to allow
completion of the new stairs to the penthouse. The sprinkler
system installation is complete and is currently being tested.
Installation of the new skylight is complete.
Cornell Addition (a.k.a. Biology/ Commons Wing)
- Walls have been framed on the ground level and mechanical
services are being installed on all floors. Installation of
mechanical piping and duct is continuing on the first and second
floors. The one remaining Commons concrete column and the top of
the elevator shaft were poured. Increased activity will continue
north of the Cornell Library due to the pouring of footings and
foundations for the new 40-seat classroom.
Chiller Plant
- Installation of the granite veneer is complete. Duct and pipe
installation is in progress. The cooling towers are being piped.
The first chiller was delivered on 7/26.
Chemistry Wing
- Steel erection is substantially complete. Elevated decks have
been poured. Astronomy area decks are complete and mechanical,
electrical and plumbing rough-in are underway.
SITEWORK:
- Chilled water piping is being installed underground from a
connection point south of Trotter Hall, north along the east side
of Beardsley Hall, to a connection point at the end of Whittier
Place during the next 3 weeks. Pedestrian traffic has been
re-routed around the front of Trotter to the new walkway to allow
excavation to begin at Beardsley.
- Two additional trenches are being cut to complete sanitary and
data line tie-ins outside the construction fence. The work area is
enclosed in orange snow fence.
PEDESTRIAN / VEHICULAR ACCESS:
- The sidewalk along the east side of Beardsley is currently
closed to pedestrians and will remain closed for a period of 3
weeks while the chilled water lines are installed. The entrance to
Beardsley will be usable in case of an emergency. The North Quad
entrance to Beardsley will remain open.
- Deliveries of concrete block, reinforcing steel, concrete and
stone will be on-going.
- Parking along Whittier Place is prohibited during the hours of
7 a.m. to 5 p.m., Monday through Friday.
- The construction work force has increased due to other
projects on north campus. Thank you for your cooperation in
respecting the areas designated as Construction Parking by using
the rugby and Dupont parking lots.
NOISE, VIBRATION, DUST, ODORS
- There will be some noise from delivery trucks and saws
throughout this period. The noise is not expected to be disruptive
to nearby buildings.
- Expect deliveries of reinforcing steel, concrete and masonry
throughout this period to generate dust on-site.
- There will be some dust generated by the on-going trenching
for the chilled water lines at Beardsley.
return to Home Page
Send message to the chair
of the Science Project User's Group, Rachel Merz
(rmerz1@swarthmore.edu)
For inquiries regarding construction issues, send message to
construction@swarthmore.edu
last updated 8/2/02
webmaster