Construction
Update as of January 31, 2002
Period 1 thru 14 February
2002
UTILITY SHUTDOWNS:
- There are no utility shut-downs planned for this period.
WORK AREAS:
Rugby Field
- A mulch path is being installed at the northeast corner of the
parking lot to facilitate passage onto the field.
Biology / Commons Wing
- Excavation of footings east of Cornell will continue
throughout this period. Concrete footings will be placed.
Foundation wall forms will be erected and concrete poured at the
areaway south of Cornell. A hole will be drilled for the elevator
piston and a steel casing will be set during this period.
Chiller Plant
- Footings are nearly complete. They will be dampproofed and
backfilled during this period.
PEDESTRIAN / VEHICULAR ACCESS:
- Parking along Whittier Place is prohibited during the hours of
7 a.m. to 5 p.m., Monday through Friday.
- The construction workforce is getting larger. Please
respect the areas designated as Construction Parking by using the
rugby lot and the south part of the Dupont lot closest to the
building.
NOISE, VIBRATION, DUST, ODORS
- There will be some noise from excavation and drilling
equipment and concrete trucks throughout this period. The noise
is not expected to be disruptive to nearby buildings.
DELIVERIES / HEAVY EQUIPMENT:
- Expect deliveries of reinforcing steel and concrete throughout
this period. There will also be movement of dump trucks around
the site. Several contractor office and storage trailers will be
delivered and set both on the site and in the north half of the
Dupont Visitors' Lot.
return to Home Page
Send message to the chair
of the Science Project User's Group, Rachel Merz
(rmerz1@swarthmore.edu)
For inquiries regarding construction issues, send message to
construction@swarthmore.edu
last updated 1/31/02
webmaster